PULASKI COUNTY (6-27) – c, according to Arkansas Department of Transportation
(ARDOT) officials.

Weather permitting, eastbound lanes on I-630 will shift onto newly constructed pavement
during overnight hours Friday night, June 28 through Monday night July 1, from 8:00
p.m. to 6:00 a.m.


The inside and middle lanes of eastbound I-630 will be closed between Baptist Hospital Drive
and University Avenue to move traffic to the new pavement, install concrete barriers and
place temporary striping. In addition, the lane shifts will move traffic onto new pavement at
the I-630 eastbound on-ramp at John Barrow Road and the eastbound on and off-ramps at
Rodney Parham Road.

All lanes of eastbound traffic may be stopped for 15-minute intervals during this time to
allow for the lane shifts. The public is advised to be cautious when traveling in the work zone,
and drivers may consider finding alternate routes as delays may occur. Traffic will be
controlled using signage and barrels. Neighborhoods adjacent to the interstate may
experience noise impacts during nighttime hours.

This project (Job CA0608) is part of ARDOT’s Connecting Arkansas Program, which is funded
through a 10-year, half-cent sales tax. Interstate 630 is being widened to four lanes in each
direction (eight total) between the Big Rock Interchange and University Avenue. More
information on this $87.4 million project is available at ConnectingArkansasProgram.com.

Drivers should exercise caution when approaching and traveling through all highway work
zones. Additional travel information can be found at IDriveArkansas.com or ARDOT.gov. You
can also follow us on Twitter @myARDOT.

CAP

19-170