Interstate 30 Construction Requires Lane Closures in Little Rock and North Little Rock

PULASKI COUNTY | Feb. 18, 2022

Work on Interstate 30 in Little Rock and North Little Rock involves weekly lane closures.

Weather permitting, the following travel impacts are expected to occur next week, beginning Monday, Feb. 21. Double-lane closures on interstate lanes will generally be limited to 11 p.m. to 4 a.m. Traffic will be controlled by construction barrels and signage. Drivers should exercise caution when approaching and traveling through all work zones.

Daytime closures (9 a.m. – 3 p.m.)

  • I-30 frontage roads (single-lane closures) between 4th and 10th Streets in Little Rock

Overnight closures (8 p.m. – 5 a.m.)

  • I-30 (single- and double-lane closures) between Roosevelt Road in Little Rock and Bishop Lindsey Avenue in North Little Rock
  • I-30/I-40 ramps or lanes (single-lane closures) at the north terminal in
    North Little Rock
  • I-630 eastbound ramp to I-30 eastbound (full closure) in Little Rock; ramp detour signed to exit to northbound frontage road
  • I-30 frontage roads (single-lane closures) between 7th and 10th Streets in Little Rock

24-Hour closures

  • I-630 eastbound ramp to I-30 eastbound (full closure) in Little Rock; ramp detour signed to exit to northbound frontage road; closed the night of February 25 to the morning of February 28
  • Sherman Street (full closure) between 2nd and 3rd Streets in Little Rock; detour signed to use River Market Avenue; street closed through mid-March

Contact: Ellen Coulter

NR 22-030

February 18, 2022