PULASKI COUNTY | July 28, 2023
Work on Interstate 30 in Little Rock and North Little Rock involves weekly lane closures.
Weather permitting, the following travel impacts are expected to occur the week of Monday, July 31.
Double-lane closures on interstate lanes will generally be limited to 11 p.m. to 4 a.m. Traffic will be controlled by construction barrels and signage. Drivers should exercise caution when approaching and traveling through all work zones.
- I-30 frontage roads (single-lane closures) between 6th Street and 10th Street in Little Rock (7 a.m. – 5 p.m.)
- I-40 frontage road eastbound (single-lane closure) to the North Hills Road Exit 154 in North Little Rock
- Cypress Street southbound (single-lane closure) between 5th and Broadway streets in North Little Rock
- Broadway Street (single-lane closures) between Cypress and Locust streets in North Little Rock
Overnight closures (8 p.m. – 5 a.m.)
- I-30 (single and double-lane closures and traffic shifts) between Roosevelt Road in Little Rock and I-40 in North Little Rock
- I-30 westbound to I-630 westbound ramp (Exit 139B) (single-lane closure) in Little Rock
- I-630 ramps onto and off 15th Street (full closures) between College Street and the I-630 interchange in Little Rock; detours will be signed
- I-30/I-40 lanes and ramps (single-lane closures) at the north terminal in North Little Rock
- I-30 frontage road southbound ramp to I-30 westbound (full closure) in Little Rock; detour signed to Roosevelt Road interchange
- I-40 frontage road eastbound (single-lane closure) to the North Hills Road Exit 154 in North Little Rock (7 p.m. – 7 a.m.)
- Cypress Street southbound (single-lane closure) between 5th and Broadway streets in North Little Rock
- Broadway Street (single-lane closures) between Cypress and Locust streets in North Little Rock
24-hour Closures
Riverfront Drive westbound (full closure) between Olive and Pine streets in North Little Rock; Riverfront eastbound converted to allow for two-way traffic
Contact: Ellen Coulter
NR 23-251