ARDOT currently utilizes Design Build (DB), Construction Manager-General Contractor (CM-GC), and Progressive Design Build (PDB) alternative project delivery methods.
Design-Build (DB) Information
Progressive Design-Build (PDB) Information
Using the Progressive Design-Build Delivery Method, ARDOT uses a procurement process to select a progressive design-build team to design and construct a project under the direct supervision and direction of the Department.

Progressive Design-Build Laws, Rules, Policies & Guidelines
Federal Authority
Arkansas Legislative Authority
ARDOT Guidelines
Construction Manager-General Contractor (CM-GC) Information
Using the Construction Manager-General Contractor delivery method, ARDOT uses a procurement process to select a Contractor to assist in the design and construct the project upon successful negotiation of Guaranteed Maximum Price.

CM-GC Laws, Rules, Policies & Guidelines
Federal Authority
Arkansas Legislative Authority
On-Call CM-GC Documents
Request For Qualifications
Request For Proposals
On-Call CM-GC Agreement
On-Call CM-GC Procurement Schedule
Projects
Design-Build Projects

CA0602 Design-Build Documents
Request for Qualifications
Request for Proposals
Request For Clarifications
Procurement Schedule
Progressive Design-Build Projects

110651 Progressive Design-Build Documents
Request for Proposals
Procurement Schedule
Project Construction Plans
CM-GC Projects
Current & Future CM-GC Projects




Educational Tools
Project Photos
Job 061331